UPPER MAI HYDROELECTRIC PROJECT

Upper Mai Hydroelectric Project is situated in the Sandakpur rural municipality, Ilam District, Eastern Development Region of Nepal. The Upper Mai Hydroelectric project (12MW) is designed as a run of-river scheme. The project is owned by  Panchakanya Mai Hydropower Limited. The hydropower project utilizes a catchment area of 53.00 km², with a design discharge of 3.14 m³/s and a net head of 374.90 m.

The diversion weir is a concrete gravity dam at 1628.0 masl, feeding into a side intake system with two rectangular orifices The project includes a 636.4 m headrace pipe and a 2075 m long inverted D shaped tunnel, connected to a 3.5 m diameter, 32.1 m high surge shaft and a 1516.96 m penstock. The powerhouse located at 1242.2 masl, houses two horizontal-axis Pelton turbines each rated at 5000 kW supported by two 6.6 kV generators.